Public Works Project List
Apr 7, 2008
Author: Alicia
Project Requests for Public Works:
Trail Board Priorities
1. Construct headwalls on the 2 culverts on the drain ditch off of Klondike Drive
2. Expand the parking lot from 6 to 10 parking slots at Turkey Lane
3. Remove asphalt in Washington Park and replace with reject sand
4. Construct a fence at Turkey Lane to restrict horseback riding
5. Remove asphalt on Centennial trail and replace with reject sand
6. Install a water bar between mile marker 0.1 and marker 0.2 on the Greenbelt
7. Gravel the road at Cedar Street
8. Curb modification to meet ADA standards on Western Avenue
9. Reconstruct the parking lot fence at Cedar Street, consider a re-design
10. Move “Cobra light” at southeast side of Steel Pony Truss bridge to the southwest corner
11. Place a sidewalk along Turkey Lane
Yearly Maintenance Requests for City Parks Department:
1. New Request: Empty garbage cans: There are 6 garbage cans total.
a. Greenbelt (4 cans)
1. Off Klondike Drive
2. mile marker 0.3
3. mile marker 1.13
4. on the west side of pond
b. Centennial trail (2 cans)
1. off of Bypass Road
2. off of Lobban Avenue
2. Maintain picnic tables: There are 2 picnic tables total.
a. Centennial trail (2 picnic tables, ok condition)
3. New Request: Remove “No hunting” sign in the Greenbelt to conform to City Ordinance
4. New Request: Line-trimming around improvements
5. Snow removal
6. New Request: Gravel/sand maintenance on Greenbelt trail, Washington trail, Eva Knepper trail